How a contractor tracks change orders and job costs
Most jobs change after the contract is signed: the customer picks a different tile, the inspector asks for more blocking, a wall hides rot. Work done on a handshake is the work that goes unpaid, and a job that looked profitable on the bid can lose money one small change at a time.
Two habits fix most of it: no change without a written, accepted price, and a running total of what the job has cost against what it is worth.
Step 1: price the bid with your cost and your markup
On the bid’s deal, add each line at what it costs you and your markup. The quote the customer sees shows the price alone, never your cost.
Step 2: make every change a change order, before the work
When the scope changes after the customer accepted the quote, make a change order from that quote with the reason. It waits for your quote approver, so nobody prices a change alone.
Step 3: have the customer accept it in writing
The customer accepts the change order on the quote page by typing their name, the same way they accepted the quote. Keep working on the change only once it says accepted.
Step 4: keep the job’s costs on the job
Give the job a budget for labor, materials and subcontractors, and what an hour of labor costs you. Log time on the job and its work orders, record parts used, and mark purchase orders for the job. Job costing adds them up against the contract and its accepted change orders.
Step 5: keep subcontractors’ papers current
Store each subcontractor’s insurance certificate and license as a document on their company, with its expiry date. Whoever looks after the company is reminded before it runs out.
What ContactRoll keeps out of it
ContactRoll keeps your bids, change orders, costs and papers. It pulls no permit, holds no retainage or escrow money and takes no payment: invoices go out from your own books.
The construction template sets up the record types, pipeline and flows this guide uses in one step: see what it adds.
Questions
Does the customer see my markup?
No. A line keeps its cost and markup for you; the quote and the change order show the price alone.
Can a later quote cancel a change order?
No. A change order belongs to the accepted quote it changes, and a later quote does not withdraw it.